How to File a Nebraska Mechanics Lien

If you have decided to file a mechanics lien in Nebraska, this step-by-step guide will break down the entire process for you. Before moving ahead with filing a mechanics lien, it’s important to note that there may be preliminary notice requirements that may have to be satisfied prior to the filing of a valid mechanics lien.

And on top of that, there are always timing requirements when it comes to the mechanics lien process — in Nebraska as well as every other state.

But if you want to move forward with a Nebraska mechanics lien on your own, just follow the steps outlined below.

Mechanics Lien Are Powerful, Legal Tools to Help Guarantee Payment on Construction Projects

Nearly everybody in the construction industry is familiar with payment problems. Slow payment, or even nonpayment, is all too common — no matter where a construction project takes place.

Construction participants don’t need to just assume payment problems are a fact of life, nor that write-offs are inevitable, however. Mechanics liens (and bond claims) – are available in all 50 states (including Nebraska of course!) and work to get construction companies to get paid fairly.

Make Sure Your Nebraska Mechanics Lien Has the Required Information

It is generally critical to make sure your mechanics lien contains all of the required information. Since mechanics liens are created by law, they require strict compliance with specific statutory requirements. Strict compliance means that the failure to provide the required information on the lien claim isn’t just a simple oversight — it can invalidate the entire lien and make it unenforceable (or in other words, useless).

While Nebraska provides some information related to the contents of a lien for work on railroads or similar utilities, the Nebraska lien laws are not clear on the requirements for the contents of a lien for other (most) projects. Note, however, that certain information is always helpful, and it is likely a best practice to include at least the same information as would be required on a railroad or utility project.

Nebraska mechanics liens should contain the following information:

1) The name of the owner;
2) The name of the claimant;
3) A description of the real property to be charged with the lien;
4) A just and true statement or account of the demand due to s/he after allowing all credits;
5) The time when such material was furnished or labor performed, and when completed; and
6) A signature verifying the lien by affidavit


Visit the Nebraska mechanics lien and notice FAQ page for more info and help


How to File a Nebraska Mechanics Lien

Now it’s time to get your Nebraska mechanics lien filed with the register of deeds of the county in which the property at the center of the construction project is located.

  1. Prepare the lien form, taking care to include all relevant information, and sign the document with the verification statement in the presence of a notary and have the affidavit notarized.
  2. Some counties in Nebraska allow for electronic recording. If your lien is to be filed in a county in which e-recording is available, that can streamline the process and ensure the proper fees are provided. If e-recording is not an option, or you don’t wish to file in that manner, send the original notarized copy to the register of deeds of the county in which property is located.
    – The lien may be delivered to the proper register of deeds via mail or FedEx, or personally “walked in” to be recorded (either by you or a courier).
    – Make sure to include the proper recording fees with the lien. Lien are often rejected for improper fees (and this can be true even if you provide too much money). Any delay caused by needing to resubmit the lien for recording takes time – and since liens are time sensitive documents, it can possibly result in a missed deadline. Recording fees vary from county to county and can be determined by calling the county register of deeds, checking on the register’s website, or asking in person if you physically bring the lien for filing. The fees are often set at one amount for the first page with an additional, smaller, amount for each additional page.
    Note that your lien document must also comply with any specific margin requirements that particular county may have, as well as potentially requiring a county-specific cover page – these can also be determined by calling the register’s office.
  3. Note that if you mailed your lien to the county for recording, or sent it via a courier, along with the proper fees for recording with the document, you will must include a self-addressed stamped envelope with return instructions to receive a copy of the recorded lien – this is important because Nebraska requires a stamped copy to be served on the property owner to complete the process.
  4. Serve a copy of the mechanics lien — see below for detailed information on How to Serve a Nebraska Mechanics Lien.

How to Serve a Nebraska Mechanics Lien

The process to obtain a valid Nebraska mechanics lien is not completed just by filing the document. A copy of the lien must be served on the property owner.

Nebraska specifies that the copy served on the property owner must be a stamped/recorded copy of the lien, and it must be served on the owner within 10 days of the lien being filed. This is a relatively short turn-around time, so if you didn’t e-record or physically bring the lien to the register for recording, it pays to keep your eyes peeled for a return copy in order to get it served immediately. Service on the property owner can be accomplished by certified mail.

Congratulations! Once the lien document has been filed and served, your Nebraska mechanics lien is ready to get you paid what you’ve earned. While mechanics liens are powerful, they can still be challenged. (And as discussed above, if the recording, timing, or notice requirements were not specifically complied with, the lien may be unenforceable.)

Finally, a Nebraska mechanics lien stays effective for 2 years from the date the lien was filed.

Even if it is a valid lien, the fact the lien was filed may not be enough to prompt payment by itself, and you may be forced to enforce your lien claim through a foreclosure action. While this ultimately ends up with received payment in nearly every case, it can sometimes be a long road to get there if a foreclosure suit is needed.

Summary
Mechanics Lien Nebraska: How to File an NE Mechanics Lien
Article Name
Mechanics Lien Nebraska: How to File an NE Mechanics Lien
Description
How to File a Nebraska Mechanics Lien. This step-by-step guide is essential reading for anyone working in the Nebraska construction industry.
Author
Publisher Name
zlien
Publisher Logo

Last Updated on Jan 15, 2019
Published on Dec 31, 2018

by

Nate, along with being a husband, father, Eagle Scout, Teen Jeopardy! contestant, and musician, is the Chief Legal Officer and General Counsel at zlien, a vertical SaaS platform designed to help construction industry participants by promoting a collaborative construction payment process. Nate was recently recognized as one of the nation's Top General Counsels, and is working to get better at it every day. Nate is a licensed attorney in Louisiana and Texas, and a graduate of Stanford University (B.A.) and Tulane Law School (J.D.). He manages and oversees the Lien Genome and zlien's products, processes, and resources, directs the Construction Payment Blog, protects zlien's interests and intellectual property, and performs general counsel duties.

Leading Thought on Construction Payment, Delivered To Your Inbox

zlien's Construction Payment Blog helps professionals in the construction industry navigate complicated payment issues. Join over 20,000 people who read our blog each month and subscribe.

Subscribe

Read Next